Brandenburg Airport

Project details

In this project me and my team's task was to renovate and extend the East wing of the Brandenburg Airport. The challenge was in executing the project without affecting airport traffic too much.

During the planning my job was to do the site plan and estimate a roadmap where different parts of the site was occupied at once so the rest could operate normally. We segmented work into four phases spanning across 7 months.

Area of site

64500 ft2

Date

2023

Status of the project

Under construction

Tools used

3ds Max, AutoCAD

Construction on the extension began in Jan. '23
Setting up scaffolding of Phase 1 – March. '23
Starting renovation of Phase 1 – May. '23